The bottleneck is no longer the chip. It is the transformer.

Lead times of 115–130 weeks for large transformers, and up to five years for high-power units.

A. Lam Infrastructure Reporter Published 10 Sep 2026 16:20 HKT 2 min read

Procurement data for the first half shows why so much announced data centre capacity has slipped. Large power transformers now carry lead times of 115 to 130 weeks, roughly two and a half years, and high-power specialised units can take up to five years.

Grid connection is the second constraint. Rack density has risen from 8–10kW to 30–50kW, and a gigawatt-scale campus draws as much power as a mid-sized city. In many regions there is no headroom, and interconnection queues exceed two years.

The consequence is that the binding constraint on AI capacity has moved from semiconductor supply to electrical infrastructure — a segment with few suppliers, long qualification cycles and its own shortage of skilled labour. Capital can be raised faster than transformers can be built.

Sources

This article draws on public disclosures, regulatory filings and market data. Figures are as of publication.